Oregon Construction Contractors (CCB) Practice Test

Disable ads (and more) with a membership for a one time $2.99 payment

Prepare for the Oregon CCB Test with our study materials. Use flashcards and multiple-choice questions with explanations and hints. Ensure you're ready for exam success!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


What type of conditions modifies the general conditions of a contract and is often prepared separately?

  1. General conditions

  2. Supplemental conditions

  3. Standard conditions

  4. Conditional clauses

The correct answer is: Supplemental conditions

Supplemental conditions are specifically designed to modify the general conditions of a contract, addressing project-specific requirements that go beyond the standard provisions typically outlined in the general conditions. These supplemental conditions can include details related to local laws, environmental regulations, or unique contractual obligations that reflect the needs of a specific project or jurisdiction. By having these conditions prepared separately, it allows for clear delineation between the overall contract requirements and the specific modifications needed for the project. This provides an organized structure that helps all parties involved to easily identify adjustments necessary for compliance and successful project execution.