Oregon Construction Contractors (CCB) Practice Test

Disable ads (and more) with a membership for a one time $2.99 payment

Prepare for the Oregon CCB Test with our study materials. Use flashcards and multiple-choice questions with explanations and hints. Ensure you're ready for exam success!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


When must a claim of lien be recorded?

  1. 75 days after the initial contract date

  2. 75 days after the first progress payment was made

  3. 75 days after the project is substantially complete

  4. 75 days after informing the owner about construction liens

The correct answer is: 75 days after the project is substantially complete

A claim of lien must be recorded within 75 days after the project is substantially complete. This timeline is significant because it provides a clear framework for contractors and subcontractors to secure their right to payment if they have not been compensated for their work. By requiring the lien to be filed within 75 days of substantial completion, the law ensures that property owners are made aware of potential claims against their property while also balancing the interests of contractors and subcontractors who need timely recourse for unpaid work. The option related to the initial contract date or the first progress payment does not align with the standard requirements for filing a lien, as these events do not directly relate to the completion status of the project. Moreover, the choice concerning informing the owner about construction liens is not applicable to the specific timeline mandated for recording a lien, which is strictly tied to the substantial completion of the project. Hence, the focus on substantial completion reflects industry practices that protect the interests of all parties involved in the construction process.