Which of the following best defines a critical activity?

  1. An activity with no float time

  2. An activity that can be delayed without consequences

  3. An activity that impacts other activities directly

  4. An optional activity in a project

The correct answer is: An activity with no float time

A critical activity is best defined as an activity with no float time. In project management, critical activities are those tasks that must be completed on schedule for the project to stay on track. They are integral to the project timeline; delays in these activities directly impact the entire project’s completion date. Because they have no float time, there is no leeway for delay without affecting project progress. Other options describe different aspects of project tasks but do not accurately characterize critical activities. For instance, an activity that can be delayed without consequences refers to non-critical activities, which have float time or scheduling flexibility. An activity that impacts other activities directly might seem relevant, but it is broader and can apply to both critical and non-critical activities, showing that it is not a defining trait. Lastly, an optional activity in a project is one that isn’t necessary for the project's completion and usually doesn’t influence the project's schedule directly. Thus, the absence of float time is a definitive characteristic of a critical activity, setting it apart from others in project management.